top of page

Portable Building Relocation + Parking-Lot & Drop-Off

Armada Elementary School had several aged portable classrooms that could not withstand the growing population, increased traffic, and educational demands. Clustered at the corner of the campus, these portable classrooms made it difficult for students to safely dropped-off or securely gather during the day. In addition to the New 2-Story Classroom Building, GOAI implemented site improvements and ADA upgrades to make the entire campus safer, more secure, and accessible for people with disabilities. Because of this, Armada Elementary was finally able to renovate and relocate some of the aged portable classrooms to more appropriate locations on campus, and in their place, develop a new parking-lot and drop-off area to assuage traffic and congestion.

Client / Owner

Project Facts

Armada Elementary School

Project Location

Moreno Valley Unified School District

Architect           Larry Buoncristiani, RA

Firm PIC            Godwin Osifeso, RA, LEED AP

DSA No.            04-11868

Est. Value          $ 140,000

Bid Value           $ 1,558,400

Final Value        $ 1,267,921

Start                   Dec 24, 2015

Completion       Mar 29, 2017

Related Project Categories

Transformation/Modernization
Elementary School
Related Projects
bottom of page